Determine the cost to finish the slab in Problem 56 using a productivity of 0.013 labor hours per square foot and an average labor rate of $31.17 per labor hour.
What will be an ideal response?
From Problem 56, the area of the slab is 1,050 sf.
Labor hour = 0.013 lhr per sf × 1,050 sf = 13.65 lhr
Labor cost = 13.65 lhr × $31.17/lhr = $425.47