Determine the cost to finish the slab in Problem 56 using a productivity of 0.013 labor hours per square foot and an average labor rate of $31.17 per labor hour.

What will be an ideal response?


From Problem 56, the area of the slab is 1,050 sf.

Labor hour = 0.013 lhr per sf × 1,050 sf = 13.65 lhr

Labor cost = 13.65 lhr × $31.17/lhr = $425.47

Trades & Technology

You might also like to view...

The maximum 60Hz voltage that can be applied to a switch for one minute without causing insulation failure is known as the _____.

a. BIL b. withstand rating c. switch kV d. fault close

Trades & Technology

Technician A says that safety glasses should be worn at all times in the automotive shop. Technician B says that ear protection should be worn at all times in the automotive shop. Who is correct?

A. A only B. B only C. Both A and B D. Neither A nor B

Trades & Technology

On a fan/limit switch what is the usual setting for the limit?

What will be an ideal response?

Trades & Technology

A series-parallel circuit consists of resistors in both series and parallel

Indicate whether the statement is true or false

Trades & Technology