Activities G, P, and R are the immediate predecessors for activity W. If the earliest finish times for the three are 12, 15, and 10, then the earliest start time for W

a. is 10.
b. is 12.
c. is 15.
d. cannot be determined.


c. is 15.

Business

You might also like to view...

Under the National Labor Relations Act, before engaging in an economic strike to achieve better wages, hours, or working conditions under a new collective bargaining agreement, a union must first contact the ________ and attempt to ________ contract

demands. A) FMCS; mediate B) FTC; mediate C) FMCS; arbitrate D) FTC; arbitrate

Business

Which of the following must a paralegal not do?

A) Interview clients and witnesses B) Draft documents and pleadings C) Maintain a calendaring system D) Give legal advice where legal rights are affected

Business

The carbon footprint measures total ________ caused directly or indirectly by an organization, a product, an event, or a person

Fill in the blanks with correct word

Business

The transition from the ________ stage to the ________ stage of the customer relationship requires the development of trust.

A. Customers as partners; customers as acquaintances B. Customers as acquaintances; customers as strangers C. Customers as acquaintances; customers as friends D. Customers as strangers; Customers as acquaintances E. Customers as friends; customers as strangers

Business