Upon receiving your copies of the contractor's CPM diagram and regular updated printouts of scheduling data, the engineer or owner should:

A. review the schedules for logic, task durations, and ability to meet specified dates.
B. file them in case of a later need to investigate delay claims.
C. quickly skim the printout, then file it, keeping the master chart on the wall.
D. study them carefully and post all changes on your master chart.
E. advise the contractor how to sequence the Work.


A

Trades & Technology

You might also like to view...

The cutting edge of a chisel is an example of a wedge

Indicate whether the statement is true or false.

Trades & Technology

?Which type of weld joint can be fitted together so that the joint forms a V-groove or square butt joint?

A. ?butt B. ?tee C. ?outside corner D. ?edge

Trades & Technology

In determining the load of the highest-rated motor, the greater of either the ampere rating from 430.22(E) or the largest continuous-duty motor full-load current multiplied by ____ shall be used in the summation.

A. 1 B. 1.25 C. 1.50 D. 1.75

Trades & Technology

Which floor plan style is well suited for a sloping lot?

A. daylight basement B. split-level C. dormer D. single-level

Trades & Technology