A contractor's estimate for a job lists $17,850.00 for excavating and grading, $2,110.50 for concrete work, $890.00 for brick work, and $480.00 for setting stone. What is the total of this estimate?

What will be an ideal response?


$21,330.50

Trades & Technology

You might also like to view...

When a note applies to a particular part on an object, it is called a(n) ____ note.

A. general B. area C. identifying D. local

Trades & Technology

In ____, no vacuum or air pressure is used to form the part. Only the force of bending, stretching, or holding the hot sheet is used.  ?

A. ?vacuum forming B. ?free forming C. ?mechanical forming D. ?drape forming

Trades & Technology

The Agriscience Fair provides the opportunity for students to compete with other students in their own school, state, and in the nation

Indicate whether the statement is true or false

Trades & Technology

While discussing power recirculating ball steering gear diagnosis:

Technician A says excessive steering wheel free play may be caused by a worm shaft bearing preload adjustment that is tighter than normal. Technician B says excessive steering wheel free play may be caused by loose steering gear mounting bolts.

Trades & Technology