What is the fastest completion time of the project with activity lengths (in days) and precedence requirements as shown in the table?
Activity Length Predecessor
A 15 --
B 7 A
C 4 A
D 8 B, C
A) 22
B) 25
C) 27
D) 30
Answer: D
You might also like to view...
The value proposition is stated in the price of a product and readily recognized by the average consumer
Indicate whether the statement is true or false
The first step in designing a _____ is to define the various entity classes and the primary keys that uniquely define each record or instance within each entity class.
Fill in the blank(s) with the appropriate word(s).
A master distributor is most likely to work in which of the following?
A) a box store B) a B2B e-commerce site C) a party plan system D) network marketing E) an experiential store
Which of the following is the correct pattern for incorporating graphs in a text?
(A) Introduce, interpret and analyze, and show. (B) Introduce, show, and interpret and analyze. (C) Show, explain, and interpret. (D) Explain, interpret, and show.