Why is a schedule not a schedule until resources have been assigned? Provide a real life example that illustrates your explanation.
Fill in the blank(s) with the appropriate word(s).
Answer will vary
Before resources are assigned it is assumed that there will be adequate resources available once the project is implemented. Without assigning resources before implementation, resource constraints will be recognized during implementation and could have negative impacts on the project's deadline.
You might also like to view...
____________________ are formally prescribed by the organization.
a. Informal communication networks b. Organizational chart c. Formal communication networks d. none of the above
Finding the lowest price is the first responsibility of the smart insurance consumer
Indicate whether the statement is true or false
Jared agrees to purchase twelve computers from Zack Enterprises, Inc for sale in Jared's department store. Twelve boxes from Zack Enterprises have just arrived at the department store. What are Jared's rights and responsibilities?
Which of the following is a breach of the broker's fiduciary duty?
A) Withholding negative information about the buyer B) Extending the listing agreement C) Collecting a net commission D) Demanding a commission when the buyer is ready, willing and able E)?None of the above