The beta distribution is used in project management to:
A) calculate slack on activities not on the critical path.
B) calculate the probability that a project will be completed within its budget.
C) calculate pessimistic and optimistic activity times.
D) determine which activity should be crashed.
E) none of the above
E
You might also like to view...
What is an engaged listener? Describe how you can become an engaged listener and why this is important for creating a meaningful and effective interview?
What will be an ideal response?
Verbal, graphical, and mathematical models depict the same phenomenon or theoretical framework in different ways
Indicate whether the statement is true or false
Which of the following is NOT a characteristic of interpersonal dialogue?
A. unscripted and unrehearsed responses B. openness to risk C. focus on a specific outcome D. tentativeness about the feelings of the other party
The Fisher Effect decomposes nominal interest rates into the ________ and the expected rate of inflation
A) expected real exchange rate B) expected real interest rate C) expected forward rate of return D) nominal exchange rate