Developing an understanding of the content and complexity of the project is the purpose of:
A) developing a project charter activity of the project planning phase.
B) setting a baseline project plan activity of the project planning phase.
C) determining project standards and procedures activity of the project planning phase.
D) describing the project scope, alternatives, and feasibility activity of the project planning phase.
E) closing down the project activity of the project planning phase.
D
Explanation: D) During the project planning phase the scope, alternative and feasibility of the project are defined.
You might also like to view...
Answer the following statements true (T) or false (F)
1. Power refers to the rights inherent in a managerial position to make decisions, give orders, and utilize resources. 2. Director of accounting is an example of a staff position. 3. Staff personnel have authority functions in that they provide advice, recommendations, and research to line managers. 4. An advantage in using centralized authority is that there is less duplication of work, because fewer employees perform the same task.
________ is the concept that organizations have a duty to all societal stakeholders to operate in a manner that takes each of their needs into account.
A. Ethics B. Corporate social responsibility C. Business savvy D. Stakeholder accountability
Which of the following criteria is not required to be met under the tax concept of income?
A. Cash must be received. B. There must be economic benefit. C. Income must be recognized. D. Income must be realized.
?Open market operations is a more flexible tool of monetary policy than changing the reserve requirements.
Answer the following statement true (T) or false (F)