In general, when should construction schedules be updated?

What will be an ideal response?


As a general rule, a construction schedule should be updated when it no longer
serves as an effective management tool. Of course, the cost of updating should be less
than the benefit derived from the effort.

Trades & Technology

You might also like to view...

The process of aerobic respiration is a significant source of which of the following gases?

A) carbon dioxide B) ammonia C) oxygen D) nitrogen E) methane

Trades & Technology

Copper wire is basically pure copper that has been hardened by:

A) Strain hardening B) Precipitation hardening C) Alloying with tin and zinc D) Heating to 1200 deg. F. (649 deg. C.) and quenching in water

Trades & Technology

To turn off an IGBT, a __________ voltage is applied to the gate.

A. negative B. positive C. either A or B

Trades & Technology

The length of a lapped splice should be 12 inches or the bar diameter times _____

a. 10 b. 15 c. 30 d. 60

Trades & Technology