Suppose you have the following project digraph. (The numbers in parentheses represent hours.)
Using the critical-path algorithm to schedule this project with five processors results in a finishing time of
A. 24 hours.
B. 20 hours.
C. 21 hours.
D. 22 hours.
E. none of these
Answer: C