What is the slack time for activity C?

Project Sand Mandala
Carrie meticulously calculated the early and late start and finish times for her latest project and recorded them using different colors of sand on a pristine slab of white marble. She used red for late start and late finish times and green for early start and early finish times. Activity durations and their identifiers were written with black sand. She finished her task and had an opportunity to admire her work only briefly before a colleague came by and swept most of it away. Sadly, this was before Carrie could record the numbers on a more permanent medium, so now she turns to you to help.

Activity Predecessor Duration Early Start Early Finish Late Start Late Finish
A - 10
B - 7 11
C A 7
D A 15 14
E B 11 19
F B 10
G D,E 24
H F 24
J C 28
K G,H,J 36

A) 3
B) 2
C) 1
D) 0


Answer: D

Business

You might also like to view...

Although there are multiple approaches to fraud investigation, most investigators tend to rely heavily on ______

a. invigilation b. surveillance c. interviews d. confrontation

Business

The audit opinion of a public company is similar to an opinion for a private company except for the public company comments will be added as to the effectiveness of internal control over financial reporting

Indicate whether the statement is true or false

Business

An understated ending inventory will produce an overstated cost of goods sold

Indicate whether the statement is true or false

Business

Learning through ______ implies that children can learn about their own culture and that it is possible to learn about the cultural patterns of another society.

A. stories B. technology C. environment D. government

Business