Discuss why notes of changes, or alterations from the construction documents, would be included on a shop drawing.

What will be an ideal response?


Notes concerning changes or differences from the original documents should be made on the shop drawing for the architect's and engineer's approval. Ultimately, they are responsible for changes in these drawings and should have the opportunity to analyze any modifications. A dialogue should occur between the fabricator and the architect and engineer about any areas needing clarification. Successful installations are the result of collaboration between the designer, fabricator, and contractor.

Trades & Technology

You might also like to view...

When laying a brick in the mortar bed, the mason's thumb should curl down over the top edge of the brick and be held slightly away from the face of the brick.

Answer the following statement true (T) or false (F)

Trades & Technology

____________________ irrigation can be used where it is not possible to surface irrigate

Fill in the blank(s) with the appropriate word(s).

Trades & Technology

Why do coil manufacturers specify both wet and dry coil static pressure drops?

What will be an ideal response?

Trades & Technology

Acid is created within a refrigeration system when:

A) Noncondensable gases collect within the condenser. B) The compression ratio within the system is significantly increased. C) Moisture is teamed with refrigerant in the refrigeration system. D) There are large quantities of air within a refrigeration system.

Trades & Technology