A project is represented by the activity durations (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table

What is the length of a feeder buffer if this project is managed using critical chain methodology?

Activity Predecessor Length Activity Predecessor Length
A -- 18 E C, D 13
B -- 16 F C 9
C A 22 G E, F 15
D B 14
A) 3.5 days
B) 2.5 days
C) 1.5 days
D) 0.5 days


B

Business

You might also like to view...

Under FIFO, the units in the ending inventory represent the oldest purchase(s)

a. True b. False Indicate whether the statement is true or false

Business

The deep pocket theory represents a misunderstanding whereby shareholders mistakenly believe that they are entitled to recover losses on investments for which the auditor provided an unqualified opinion on the financial statements

a. True b. False Indicate whether the statement is true or false

Business

Similar to financial accounting reports, management accounting reports are standardized in format

Indicate whether the statement is true or false

Business

Hispanic workers are projected to be about what percentage of the workforce by 2050?

A. 2 percent B. 8 percent C. 15 percent D. 24 percent E. 43 percent

Business