Assume that an assembly line has three tasks that must be completed (in order, A, B, and C). The tasks have processing times of 12, 15, and 10 minutes per unit, respectively. If the assembly line operates for 480 minutes per day with a desired output of 50 units per day, what is assembly line efficiency?
a. Less than 90%
b. 96%
c. Greater than 98%
d. Cannot be determined from the information given
c. Greater than 98%
You might also like to view...
Which of the following need NOT be immediately paid by a bank?
A) A cheque dated more than 2 months prior to the date it is presented for payment. B) A post dated cheque presented early C) A bill of exchange marked "payable at sight" D) Both A and B E) Both B and C
For each of the following products or services, indicate the most important customer quality attributes and the most important customer quality tradeoffs. (a) Personal computer(b) Legal representation in divorce court(c) New home purchase(d) Meals in a fast food restaurant(e) Airline travel(f) Prom dress(g) Cruise ship vacation(h) Auto repair
What will be an ideal response?
________ refers to a quality emphasis that encompasses the entire organization, from supplier to customer
Fill in the blanks with correct word
A set of estimates which corresponds to the worst and best case outcomes is often desired in
preparing a financial forecast. Indicate whether the statement is true or false