Using the P E R T diagram in Figure below determine the answers:
a. What activities can you expedite to complete the project a week ahead of schedule?
b. Suppose Activity E is the least costly activity to expedite. What happens if you try to expedite the project by more than one week? Explain.
The activities can you expedite to complete the project a week ahead of schedule are determined by the critical path, A-E-I-D (refer to the solution for Problem 19).
Activity E is the least costly activity to expedite but since activity A-E is 12 weeks and F-G is 11 weeks, if you try to expedite the project by more than one week A-E-I-D will no longer be the critical path.
You might also like to view...
The routines that communicate directly with hardware are all concentrated in the UNIX __________.
a. device driver b. kernel c. shell d. none of the above
What method of the String class would tell you the last position of a character in a String object?
What will be an ideal response?
A binary digit is referred to as a ________
A) bit B) byte C) microbit D) bite
One extremely important advantage of using integer expressions as subscripts is that it allows sequencing through an array by using a loop.
Answer the following statement true (T) or false (F)