A _____ consists of senior managers representing the business and information technology organizations—to provide guidance and support to the project.
a. quality control team
b. project steering team
c. scope management team
d. project development team
b. project steering team
In addition to the development team, each project should have a project steering team, made up of senior managers representing the business and information technology organizations— to provide guidance and support to the project. The number of members on the steering team should be limited (three to five) to simplify the decision-making process and ease the effort to schedule a quorum of these busy executives.
You might also like to view...
In order to ensure proper tracking and management, the activities required to execute the change should be documented in a detailed ____.
A. statement of work B. incident report C. after action report D. contract
If content is unreadable, in what category does the Accessibility Checker place this issue?
A) Tip B) Suggestion C) Error D) Warning
Constants that are used as arguments in expressions can be defined as ________ that do not change
A) objects B) values C) variables D) functions
You can create an empty element in an XML document by adding a ____ before the tag's closing bracket to close the element.
A. pound sign (#) B. square bracket (]) C. single slash (/) D. back slash (\)