Make a judgment as to whether there are times when adding people to a late project can help improve its delivery time.
What will be an ideal response?
Over the years, empirical data and theoretical analysis have demonstrated that project schedules are elastic. That is, it is possible to compress a desired project completion date (by adding additional resources) to some extent. It is also possible to extend a completion date (by reducing the number of resources). If you must add people to a late project, be sure that you've assigned them work that is highly compartmentalized.
You might also like to view...
Which of the following relative pathnames is interpreted as "the rock.htm file is in the same folder as the current file"?
A. /rock.htm B. ./rock.htm C. ../rock.htm D. rock.htm
Which of the following values for left and right margins centers the layout?
A. center B. default C. equal D. auto
To convert a diagram to a bulleted list, after selecting the diagram, the next step is to click the Convert button on the SmartArt Tools Design ?tab, in the Reset group. _________________________
Answer the following statement true (T) or false (F)
On the Style button, the _________________________ style allows you to specify exact pixel values for the marquee's height and width.
Fill in the blank(s) with the appropriate word(s).