What are four questions that must be asked in evaluating a delay claim in which CPM is going to be employed?
What will be an ideal response?
Certain commentators have stated that the following four questions must be
asked in evaluating a delay claim in which CPM is going to be employed: (1)
how was the project actually constructed? (2) What are the differences
between the project as planned and as constructed with respect to activities,
sequences, durations, manpower, and other resources? (3) What are the
causes of the differences or variations between the project as planned and
the actual performance? And (4) what are the effects of the variances in
activities, sequence, duration, manpower, and other resources as they relate
to the costs experienced, both by the contractor and by the owner?
You might also like to view...
?What type of product is made by blending microscopically small hollow balls of glass or plastics in a resin matrix binder?
A. ?syntactic plastics B. ?Styrofoam C. ?sandwich composites D. ?structural foam
What DLI level is well suited to most medium light requiring floral potted crops in the greenhouse?
What will be an ideal response?
The unused input for a NOR gate should be tied to
A) ground. B) another unused input. C) HIGH. D) both B and C
Graph the generalized derivative of g(t) = 3 sin (?t /2) rect(t) .
What will be an ideal response?