Product A is made from 2 Bs and 1 C. Lead times for A, B, and C are 2, 3, and 2 weeks respectively. Currently there are 2 Bs and a 5 Cs on hand, with 5 of each scheduled to arrive at the end of week 1

If 20 As are needed during week 4, can the order be completed (it is the start of week 0 currently)?


To produce 20 As requires 40 Bs and 20 Cs at the start of week 2. Since the lead time for B is greater than 2 weeks the order cannot be completed on time.

Business

You might also like to view...

Gaining information about one's competitors' activities so that you can anticipate their moves and react appropriately is called   

A. strategic forecasting. B. corporate espionage. C. contingency planning. D. trend analysis. E. competitive intelligence.

Business

Open-ended questions that respondents answer in their own words are called unstructured questions

Indicate whether the statement is true or false

Business

Integrated marketing communications involves carefully coordinating a company's many communications channels to deliver a clear, consistent, and compelling message about the organization and its products

Indicate whether the statement is true or false

Business

Liquidity ____ for the two companies must be examined carefully

A) ratios B) ratioes C) ratio's

Business