The ____ constraint schedules the Start date of the task on or after the date that you specify.

A. Must Start On
B. As Soon As Possible
C. Start No Later Than
D. Start No Earlier Than


Answer: D

Computer Science & Information Technology

You might also like to view...

What is another name for panels?

A. windows B. floating panels C. work windows D. moving panels

Computer Science & Information Technology

Which of the following is a typical responsibility of the initiating process group?

A. setting the project goal B. identifying the project manager C. identifying project budget and quality considerations D. entering project tasks, durations, and relationships

Computer Science & Information Technology

What steps do you need to take to use special characters in your cookies?

What will be an ideal response?

Computer Science & Information Technology

Grant is modifying the structure of his worksheet. Grant presses F8 to enable ____ mode.

A. Edit B. Insert C. Select D. Delete

Computer Science & Information Technology