What is required in order for a contractor to protect himself or herself when a constructive change occurs on a project?

What will be an ideal response?


In order for a contractor to protect himself or herself when a constructive change occurs on a project, and the engineer refuses to issue a change order, the contractor should notify the engineer that he or she intends to file a claim to be compensated for what they interpret to be additional work. In this situation, the contractor is claiming that a constructive change occurred and that a change order should have been issued for the work. The contractor will still perform the work but a claim will be filed for additional compensation that will be reviewed during negotiations, arbitration, or litigation depending on which dispute resolution method is used for a project.

Trades & Technology

You might also like to view...

_________________________ on an isometric drawing are parallel or perpendicular to the front, top, or profile viewing planes.

Fill in the blank(s) with the appropriate word(s).

Trades & Technology

Indirect active solar heating systems usually circulate _____.

a. an antifreeze solution in the closed loop b. a synthetic oil blend in the closed loop c. deionized water in the open loop d. an antifreeze solution in the open loop

Trades & Technology

Condemned carcasses usually represent about five percent of all carcasses inspected

Indicate whether the statement is true or false

Trades & Technology

The proper wiring sequence for a potential relay is:

a. 5 (start), 2 (common), 1 (run) b. 5 (common), 2 (start), 1 (run) c. 5 (run), 2 (common), 1 (start)

Trades & Technology