What is required in order for a contractor to protect himself or herself when a constructive change occurs on a project?
What will be an ideal response?
In order for a contractor to protect himself or herself when a constructive change occurs on a project, and the engineer refuses to issue a change order, the contractor should notify the engineer that he or she intends to file a claim to be compensated for what they interpret to be additional work. In this situation, the contractor is claiming that a constructive change occurred and that a change order should have been issued for the work. The contractor will still perform the work but a claim will be filed for additional compensation that will be reviewed during negotiations, arbitration, or litigation depending on which dispute resolution method is used for a project.
You might also like to view...
_________________________ on an isometric drawing are parallel or perpendicular to the front, top, or profile viewing planes.
Fill in the blank(s) with the appropriate word(s).
Indirect active solar heating systems usually circulate _____.
a. an antifreeze solution in the closed loop b. a synthetic oil blend in the closed loop c. deionized water in the open loop d. an antifreeze solution in the open loop
Condemned carcasses usually represent about five percent of all carcasses inspected
Indicate whether the statement is true or false
The proper wiring sequence for a potential relay is:
a. 5 (start), 2 (common), 1 (run) b. 5 (common), 2 (start), 1 (run) c. 5 (run), 2 (common), 1 (start)