A noncritical path activity?

a. Has zero slack time
b. Contributes directly to the duration of the project
c. Has zero slack time and contributes directly to the duration of the project
d. Neither has zero slack time nor contributes directly to the duration of the project


d. Neither has zero slack time nor contributes directly to the duration of the project

Business

You might also like to view...

The common language used in academic and workplace settings is called ________

A) slang B) colloquial C) Standard English D) jargon

Business

The inventory turnover of Long Corporation is 16, and its closing inventory is $20,000. Assuming there are 360 days in a year, the company's inventory conversion period is:?

A. ?22.50 days. B. ?24.25 days. C. ?32.50 days. D. ?42.75 days. E. ?50.75 days.

Business

Customers at an amusement park arrive at the rate of 10 customers per hour. The entry booth is staffed by one employee. The mean service time at the booth to provide service to each customer is 5 min. The arrival rate follows a Poisson distribution, and the service time at the booth follows a negative exponential distribution. Determine the average number of customers waiting in line.

A. 3.23 customers B. 4.17 customers C. 8 customers D. 7.65 customers

Business

Salem Corporation is conducting a time-driven activity-based costing study in its Order Fulfillment Department. The company has provided the following data to aid in that study:?Activity cost pool:Time-driven activity rate (cost per unit of activity) ?Processing Orders$4.92?Preparing Deliveries$10.66?Handling Returns$16.40?Cost Object Data:Customer JCustomer K?Number of orders processed2722?Number of deliveries prepared188?Number of returns handled01Required:Using time-driven activity-based costing, determine the total Order Fulfillment Department cost assigned to each customer.

What will be an ideal response?

Business