Use linear interpolation to estimate total units at 5:00 P.M.

What will be an ideal response?


![15138|408x205](upload://wOOuVNmIshy9148jWox5foYyHyQ.jpeg)

Total production at 5:00 P.M. is estimated to be 16077.8 units.
Check by units per minute:
Between 4:07 P.M. and 5:01 P.M. (54 minutes)
Units grow by (161 10 – 14371) or 1739 units.
Thus, units per minute are 1739 / 54 = 32.204 (units/min)
5:00 P.M. is 53 minutes after 3:10 P.M.,
Thus, production at 5:00 P.M. is 32.204 (units/min) * 53 (min) This equals 1706.8 units more than at 4:07 P.M.
Therefore, at 5:00 P.M. the total units are:
14371 + 1706.8 = 16077.8 units
Note: The reasoning in the check follows the formula, piece by piece. Also notice that the production rate (units per minute) between 2:05 P.M. and 3:10 P.M. is less than half the production rate between 3:10 and 4:07. Thus, the data in the table is not linear and the estimates we make by assuming it is linear are only rough.

Computer Science & Information Technology

You might also like to view...

You can change the margins of the pages of a report by clicking the ____ button on the Print Preview tab.

A. Page Setup B. Page Margins C. Page View D. Page Layout

Computer Science & Information Technology

In the accompanying figure, item 2 represents a(n) ____.

A. variable B. compiler C. algorithm D. interpreter

Computer Science & Information Technology

Method ___________ of class Process can open files and web pages, similar to the Run... command in Windows.

Fill in the blank(s) with the appropriate word(s).

Computer Science & Information Technology

The textbook refers to four interrelated components of the database concept. Which of the following is not one of the components?

A. the database management system B. the database administrator C. the physical database D. the conceptual database

Computer Science & Information Technology