Critical time is the amount of time that the task could be late without pushing back the completion date of the entire project.
Answer the following statement true (T) or false (F)
False
Rationale: Slack time is the amount of time that the task could be late without pushing back the completion date of the entire project.
You might also like to view...
For which of the following would polymorphism not provide a clean solution?
a. A billing program where there is a variety of client types that are billed with different fee structures. b. A maintenance log program where data for a variety of types of machines is collected and maintenance schedules are produced for each machine based on the data collected. c. A program to compute a 5% savings account interest for a variety of clients. d. An IRS program that maintains information on a variety of taxpayers and determines who to audit based on criteria for classes of taxpayers.
Broadband ISDN services will most likely be deployed
a. using only copper cabling b. using only fiber optic cabling c. using copper cabling for long distances and fiber optic cabling for a short distance d. using fiber optic cabling for long distances and copper cabling for a short distance
In examining the volume properties of a disk, the _______ status is normal and an active partition has been identified as the primary partition from which the operating system is booted
a. Healthy b. Active c. Passive d. Formatted
Which kind of license is a legal agreement that permits users to install the software on multiple computers, usually at a volume discount?
A. network B. distributed C. site D. multipurpose