Job Time Since Order Arrived (days) Processing

Time (days) Due Date (days from now)
A 8 2 7
B 7 8 16
C 7 4 4
D 4 10 17
E 3 5 15
F 2 12 18

Use the information in the preceding table and sequence the six jobs using FCFS, SPT, and

EDD. Calculate the average flow times, average early times, and average past due.


FCFS
Job Start
Time Finish Time Flow
Time
A 0 2 10
B 2 10 17
C 10 14 21
D 14 24 28
E 24 29 32
F 29 41 43

Average Flow Time = 25.17
Average Early Time = 1.83
Average Past Due = 9.00

SPT
Job Start
Time Finish Time Flow
Time
A 0 2 10
C 2 6 13
E 6 11 14
B 11 19 26
D 19 29 33
F 29 41 43

Average Flow Time = 23.17
Average Early Time = 1.50
Average Past Due = 6.67

EDD
Job Start
Time Finish Time Flow
Time
C 0 4 11
A 4 6 14
E 6 11 14
B 11 19 26
D 19 29 33
F 29 41 43

Average Flow Time = 23.50
Average Early Time = 0.83
Average Past Due = 6.33

Business

You might also like to view...

The selection of a particular inventory valuation method has a significant effect on certain key ratios

a. True b. False Indicate whether the statement is true or false

Business

Raven Company has a target of $70,000 pre-tax income. The contribution margin ratio is 30%. What amount of dollar sales must be achieved to reach the goal if fixed costs are $36,000?

A. $36,000. B. $420,000. C. $353,333. D. $23,333. E. $300,000.

Business

________ is any interference in the communication process that blocks perfect understanding.

A. Reinforcement B. An amplifier C. Noise D. Ambiguity E. A cue

Business

What synchronizes team members' activities in a way that makes them mesh effectively and seamlessly?

A. cohesion B. coordination C. groupthink D. confidence building E. affect management

Business