Case-Based Critical Thinking QuestionsCase 1-2Your supervisor has required that you begin to use Project to manage an onslaught of new projects that your team has just absorbed, but you are uncertain which version to use.Your manager informs you that you will be collaborating with others and needing enterprise project management capabilities. Which version of Project do you decide to use?
A. Project Standard
B. Project Professional
C. Project Server
D. None of the above
Answer: B
You might also like to view...
Which of the following is TRUE about the Recent Documents list in Office 2013?
A) It constantly changes. B) It is accessed from the Home tab. C) All files located on your hard drive can be accessed from it. D) It can be quickly accessed with the F10 key.
In Project 2013, ________ moves a successor task forward in time so the Start date between the tasks become further apart
A) lead time B) status date C) timescale D) lag time
Trojans similarly to viruses and worms can spread themselves once on the system
Indicate whether the statement is true or false.
Computer–based espionage is directed only at corporations
Indicate whether the statement is true or false.