Identify and describe the four parameters used to calculate the critical path for CPM


Early start time (ES): the earliest time at which an activity can start, considering the beginning and ending times for each of the preceding activities.

Early finish time (EF): the sum of the early start time (ES) and the time required to complete the activity.

Late start time (LS): the latest time at which an activity can start, considering all the precedence relationships, without delaying the completion time for the project.

Late finish time (LF): the sum of the late start time and the time required to complete the activity.

Business

You might also like to view...

Apology strategies are most often used in situations in which:

A) the violation was a major situation affecting a large number of people B) the violation was minor or the company cannot escape being found guilty C) an individual within the company has acted inappropriately, but the company itself has not D) legal charges have been filed against the company or someone in the company

Business

The ability to communicate effectively is one of the most important skills employees can have

Indicate whether this statement is true or false.

Business

Once the FASB has established an accounting standard, the

a. standard is continually reviewed to see if modification is necessary. b. standard is not reviewed unless the SEC makes a complaint. c. task of reviewing the standard to see if modification is necessary is given to the AICPA. d. principle of consistency requires that no revisions ever be made to the standard.

Business

Which sentence uses correct capitalization?

A) Either the company President or Vice President will address the staff on Monday. B) The Marketing Manager discussed ways to attract more customers to the website. C) Can you tell me, Professor, when our tests will be corrected?

Business