When a request is made for the contractor to provide additional work which was not originally specified in the contract, we call this request __________________

A. a unit price
B. a lien
C. a change order
D. a service agreement


C

Trades & Technology

You might also like to view...

A half-wave rectifier is connected to 277 V AC. What is the average DC voltage?

a. 121.3 b. 122.5 c. 123.9 d. 124.6

Trades & Technology

A certain series of standard logic gates have device numbers with prefixes of 54 or 74. These numbers represent

A) the propagation delay. B) the manufacturer's date code. C) military or commercial grade. D) the amount of power that can be dissipated.

Trades & Technology

Determine whether or not the systems with these frequency responses are causal.

Trades & Technology

Electric current is the fundamental SI electrical dimension, with the ampere (A) as its unit. Determine units for the following quantities as combinations of fundamental SI units.

(a) Electric power (b) Electric charge (c) Electric potential difference (d) Electric resistance (e) Electric capacitance

Trades & Technology