What is the cost variance of Project Makeready based on the data in the earned value table shown below?
Activity 7 14 21 28 35 42 49 Plan % Complete
Install fixtures 325 250 575 100%
Refinish floors 550 85 635 100%
Replace doors 350 275 625 100%
Complete tiling 1,200 565 1,765 80%
Install back door 875 225 1,100 70%
Landscaping 200 350 550 25%
Monthly Plan 325 800 435 1,475 1,440 425 350 5,250
Monthly Act 550 550 550 1,100 1,650 550 1,100
A) -$1,896
B) -$1,096
C) -$800
D) -$406
A
You might also like to view...
Describe sexual harassment as defined by the Equal Employment Opportunity Commission (EEOC).
What will be an ideal response?
A stall tends to mean that the customer appreciates the benefits of a product but is unwilling to engage in negotiations
Indicate whether the statement is true or false
Rewards must meet the demands of ______ to be useful in stimulating desired behavior.
A. employers B. managers C. employees D. equity
The substance over form doctrine allows the IRS to look through the legal formalities of a transaction to determine its true economic nature.
Answer the following statement true (T) or false (F)