Average completion time for a schedule sequence at a work center is the ratio of:
A) total processing time to the number of jobs.
B) total flow time to total processing time.
C) total flow time to the number of jobs.
D) total processing time plus total late time to the number of jobs.
E) total flow time plus total late time to the number of jobs.
C
You might also like to view...
Kevin is a salesperson selling electronic goods. A customer complains about problems with the music player purchased by him the previous week. He requests a replacement. Kevin explains the store's exchange policies and asks the customer to fill out a complaint form. Therefore, Kevin is dealing with the customer's problems with
A. distributive fairness. B. perceptual equity. C. procedural fairness. D. consistent fairness. E. service equity.
What is it called when a subordinate respectfully confronts or challenges a supervisor regarding a work related issue?
A. authentic leadership B. servant leadership C. courageous followership D. whistle blowing
A system that provides a real-time integrated view of a company’s core business processes through information sharing to tie together the critical components of an organization to achieve cross-functional collaboration is ______.
A. material requirements planning (MRP) B. manufacturing resource planning (MRP II) C. enterprise resource planning (ERP) D. distribution requirements planning (DRP)
Some constitutional protections apply to business entities.
Answer the following statement true (T) or false (F)