What are work breakdown structure elements that must be completed to conclude the project deliverables?

A) Activities
B) Tasks
C) Work packages
D) Milestones


C

Business

You might also like to view...

Corrine, a customer service manager, tracks monthly complaints and has been trying over the past six months to reduce them to fewer than 0.2% with additional training for her staff. She is engaged in

A. controlling. B. organizing. C. measuring. D. leading. E. planning

Business

An oil tanker crashes off the coast of California. It dumps millions of gallons of oil into the ocean. Environmental experts estimate the damages at approximately $100 million dollars. During the investigation of the crash, it is suspected that the ship's captain was intoxicated while piloting the ship, and it was this negligence that led to the crash. Is the ship owner liable for the damages? Why or why not? What affect might the captain's negligence have on the amount of the owner's liability, if any?

What will be an ideal response?

Business

A company purchased mining property for $4,875,000 containing an estimated 15,000,000 tons of ore. In Year 1, it mined 689,000 tons of ore and in Year 2, it mined 935,000 tons. Calculate the depletion expense for Year 1 and Year 2 and determine the book value of the property at the end of Year 2.$4,875,000/15,000,000 tons = $0.325 per tonYear 1: 689,000 tons * $0.325 per ton = $223,925Year 2: 935,000 tons * $0.325 per ton = $303,875

What will be an ideal response?

Business

Women and men now each make up almost half of the workforce in the U.S.

Answer the following statement true (T) or false (F)

Business