The most pessimistic time for a task is 28 days. The most optimistic time for the same task is one fourth of the pessimistic time. Calculate the variance for the duration of the activity.

a. 8.75
b. 12.25
c. 14.85
d. 10.50


b. 12.25

Business

You might also like to view...

The service-quality model highlights the main requirements for delivering high service quality. Name and describe the five gaps that cause unsuccessful delivery

What will be an ideal response?

Business

EcoBean, a chain of cafes, has introduced a Special Shopper Card that allows customers to pay in advance for coffee and snacks. This effort by EcoBean management is most likely an example of ________

A) market development B) product development C) diversification D) market penetration E) product adaptation

Business

In a liquidation, partners are given back the assets that they originally invested

Indicate whether the statement is true or false

Business

Which of the following alternative dispute resolution methods does not involve a neutral third person?

A) negotiation and settlement B) early neutral case evaluation C) minitrial D) mediation

Business