Scrum uses a series of coordinated meetings to manage the development process. During which of the following are goals and the general plan for the project established?

A. Release planning meeting
B. Sprint planning meeting
C. Sprint review meeting
D. Daily scrum meeting
E. Sprint retrospective meeting


Answer: A

Business

You might also like to view...

Because the researcher is often not familiar with the foreign product market to be examined, qualitative research is crucial in international marketing research

Discuss the issues a company should consider before using projective techniques in international marketing research.

Business

The general rule for passage of title is that title passes when the buyer acquires possession of the

goods. Indicate whether the statement is true or false

Business

What was the Wrigley company's concern in the use of Skittles in honoring Trayvon Martin?

a. That the company would be associated with murder b. That it would be perceived as capitalizing on the death of a teen c. That its brand would suffer d. None of the above

Business

Which of the following statement(s) is/are true concerning the Montreal Protocol on Substances that Deplete the Ozone Layer?

A) The United States, Mexico and Canada signed it. B) It was not signed by the United States but was signed by 23 other countries. C) It is a treaty that requires all signatories to reduce their production and consumption of all chemicals. D) It is a treaty that requires all signatories to reduce their production and consumption of only CFC's.

Business