A network consists of the activities in the following list. Times are given in weeks
Activity Preceding Time
A -- 8
B -- 3
C A 7
D A, B 3
E C 4
F D 6
a. Draw the network diagram.
b. Calculate the ES, EF, LS, LF, and Slack for each activity.
c. What is project completion time?
(a)
(b ,c)
Results
Task Early Start Early Finish Late Start Late Finish Slack
A 0 8 0 8 0
B 0 3 7 10 7
C 8 15 8 15 0
D 8 11 10 13 2
E 15 19 15 19 0
F 11 17 13 19 2
Project 19
You might also like to view...
When a new partner purchases the entire interest of an old partner, the new partner's capital account should be credited for the amount he or she paid to the old partner
a. True b. False Indicate whether the statement is true or false
Performing at a high level and conducting oneself with purpose and pride is an example of what?
A) Ethical behavior B) Strong communication skills C) Being a team player D) Ethics E) Professionalism
A(n) ________ occurs when a respondent reaches a certain point, and then decides not to answer any more questions for the survey
A) refusal B) break-off C) item omission D) perplexing situation E) desertion
Patrick prepares a presentation of a research paper that begins with the major idea. He then realizes that the topic could be antagonizing and may not please his audience. In this scenario, which of the following should Patrick use??
A) ?The deductive approach B) ?The inductive approach C) ?Metacommunication D) ?Excommunication