Describe potential users of a construction schedule
What will be an ideal response?
Any party involved in the construction process in any way is a potential user
of the schedule. The most obvious individuals would be the supervisory personnel on
the construction site (foremen and superintendents) who would use the information to
communicate with their crews and also with subcontractors. Subcontractors might be
regular users of the schedules because of their need to know when their services will
be required on site. Major vendors will also want to know the project status in order
to plan their material deliveries.
Top managers of the construction firm and representatives of the facility owner would
also be regular users of the schedule, although their interest will be of a more generic
nature to monitor the general status of the project. Sureties and financial lenders may
similarly want to have a general idea of how the project is progressing.
You might also like to view...
You have a Mod-8 counter and a Mod-16 counter. Using all the T-FF sub "s" from both counters you can make Mod-N counter. The maximum value for N =_____.
Fill in the blank(s) with the appropriate word(s).
What are the six degrees of freedom?
What will be an ideal response?
Switch and relay input contacts in the ladder diagram electrical control circuit are often configured to implement _______________ logic expressions that determine the logical operation of the control circuit.
Fill in the blank(s) with the appropriate word(s).
Explain how a compression fitting works
What will be an ideal response?