How should you, the director, proceed when according to the time line you should be doing "notes" but you still haven't finished the rehearsal?
A) continue rehearsing and do notes when finished with the rehearsal
B) interrupt the rehearsal and do notes
C) change the time line to reflect the actual progress
D) continue rehearsing and have the floor manager do notes with the PA
E) do notes with the PA and have the floor manger continue the rehearsal
B