Determine the slack for activity F
Consider the following project.
Activity Immediate Processor Activity Time (days)
A - 6
B - 8
C A, B 5
D B 4
E C 7
F C, D 3
G D 6
H E, F, G 5
A) 2 days
B) 3 days
C) 4 days
D) 5 days
Answer: C
You might also like to view...
As stated in the textbook, employees have become more empowered through ______.
A. decentralization B. globalization C. centralization D. cross-functional teams
A company pays an employee $3,000 for a five day work week, Monday - Friday. The adjusting entry on December 31, which is a Wednesday, is debit Wages Expense, $600 and credit Wages Payable, $600
Indicate whether the statement is true or false
One difference between the U.S. and EU approach to antitrust law is that
A. the EU avoids competition, whereas the U.S. seeks it. B. the U.S. focus is on impact on competition, whereas the EU focus is on the consumer. C. the U.S. follows the per se concept, wherein actions are illegal whether they have done harm. D. the EU forbids market dominance by cartels, no matter the conditions, whereas the U.S. does not.
The Code permits the seller to recover the price plus incidental damages in which of the following situation(s)?
a. Where the buyer has accepted the goods. b. Where conforming goods have been lost or damaged before risk of loss has passed to the buyer. c. Where the goods have been identified to the contract and there is a ready market available for their resale at a reasonable price. d. None of these. e. All of these.