Distinguish between a macroscopic schedule and a microscopic schedule.
What will be an ideal response?
During early stages of project planning, a macroscopic schedule is developed. This type of schedule identifies all major process framework activities and the product functions to which they are applied. As the project gets under way, each entry on the macroscopic schedule is refined into a detailed schedule. Here, specific software actions and tasks (required to accomplish an activity) are identified and scheduled.
You might also like to view...
Column headings or row labels can be repeated on multiple-page printouts using the Print Titles Page Setup option
Indicate whether the statement is true or false
By using CSS to style headers and other text elements, rather than using images containing text, your pages will download slower.
Answer the following statement true (T) or false (F)
Touch and hold an object and then move it with a fingertip to complete the ____ gesture.?
A. ?drag B. ?swipe C. ?double-tap D. ?pinch
A function can invoke a second function, which in turn invokes the first function; this type of recursion is referred to as ____ recursion.
A. direct B. mutual C. self-referential D. tail