Distinguish between a macroscopic schedule and a microscopic schedule.

What will be an ideal response?


During early stages of project planning, a macroscopic schedule is developed. This type of schedule identifies all major process framework activities and the product functions to which they are applied. As the project gets under way, each entry on the macroscopic schedule is refined into a detailed schedule. Here, specific software actions and tasks (required to accomplish an activity) are identified and scheduled.

Computer Science & Information Technology

You might also like to view...

Column headings or row labels can be repeated on multiple-page printouts using the Print Titles Page Setup option

Indicate whether the statement is true or false

Computer Science & Information Technology

By using CSS to style headers and other text elements, rather than using images containing text, your pages will download slower.

Answer the following statement true (T) or false (F)

Computer Science & Information Technology

Touch and hold an object and then move it with a fingertip to complete the ____ gesture.?

A. ?drag B. ?swipe C. ?double-tap D. ?pinch

Computer Science & Information Technology

A function can invoke a second function, which in turn invokes the first function; this type of recursion is referred to as ____ recursion.

A. direct B. mutual C. self-referential D. tail

Computer Science & Information Technology