A resident project representative should be held responsible for:

A. informing sub-contractors of the need of materials.
B. keeping the architect/engineer informed as to the progress of the work.
C. keeping the general contractor informed as to the job schedule
D. acting as liaison between jurisdictional agencies.
E. safety on or about the project site.


B