All of the following are reasons why project costs may exceed estimated prices EXCEPT ________.
A. actual productivity does not meet anticipated productivity.
B. subcontractors or materials suppliers fail to meet obligations.
C. takeoff quantities are too high.
D. takeoff quantities are too low.
Answer: C