All of the following are reasons why project costs may exceed estimated prices EXCEPT ________.

A. actual productivity does not meet anticipated productivity.
B. subcontractors or materials suppliers fail to meet obligations.
C. takeoff quantities are too high.
D. takeoff quantities are too low.


Answer: C

Trades & Technology

You might also like to view...

The demand for skilled dog groomers has grown faster than average

Indicate whether the statement is true or false

Trades & Technology

A published invitation to bid is used in competitive bidding for ____________________ projects more than residential projects

Fill in the blank(s) with correct word

Trades & Technology

What combination of symptoms only occurs on a unit with an inefficient compressor?

a. Low superheat and high subcooling b. Low suction pressure and high head pressure c. High suction pressure and low head pressure d. High suction pressure and high head pressure

Trades & Technology

In a schematic, a wire is labelled "0.8 BLK/WHT." This wire is __________

A) White with a black stripe B) 0.8 mm diameter C) Both A and B D) Neither A nor B

Trades & Technology