Item A has a lead time of 2 weeks and requires two units of Item B and three units of Item C. Item B has a lead time of 4 weeks and Item C has a lead time of 1 week. What should the planning horizon of the MRP be?
A. 2 weeks
B. at least 6 weeks
C. always less than 6 weeks
D. 3 weeks
B. at least 6 weeks
You might also like to view...
Modular design attempts to combine the advantages of standardization with ______.
A. economic order quantity B. economies of scale C. customization D. sustainability
The direct materials price standard is a carefully derived estimate or projected amount of what a particular type of direct material will cost when purchased during the next accounting period
Indicate whether the statement is true or false
As a consequence of many manufacturing firms attempting to reduce the number of suppliers with which they deal, vendors that supply high-quality products and reliable delivery schedules may expect increased business
Indicate whether the statement is true or false
Generally, which of the following media outlets relies on a mix of visual and auditory techniques and is typically very expensive?
A. Internet B. radio C. television D. newspaper E. billboards