The following table contains a list of activities, with early- and late-start and finish times and crash costs for the network shown in the figure. All start and finish times and crash costs are on a per-week basis

Each activity can be reduced by one week at the most.
a. Determine the uncrashed activity lengths for activities A though K.
b. Determine the minimum completion cost for this project if each week carries a fixed cost of $1,000.

Activity ES EF LS LF Crash Cost/week
A 0 5 0 5 $1,100
B 5 9 13 17 $250
C 5 11 5 11 $1,200
D 0 6 1 7 $350
E 6 10 7 11 $900
F 9 14 17 22 $875
G 11 17 16 22 $1,500
H 11 18 11 18 $500
I 18 26 18 26 $300
J 17 21 22 26 $625
K 26 34 26 34 $750


Activity lengths for A—K can be found by subtracting the early start of each activity from the late start of each activity.

The activity lengths appear in this table:
a.
Activity Length LS LF Crash Cost/week
A 5 0 5 $1,100
B 4 13 17 $250
C 6 5 11 $1,200
D 6 1 7 $350
E 4 7 11 $900
F 5 17 22 $875
G 6 16 22 $1,500
H 7 11 18 $500
I 8 18 26 $300
J 4 22 26 $625
K 8 26 34 $750

b.
The critical path is ACHIK = 34 weeks. Other paths are DEHIK = 33; ACGJK = 29; DEGJK = 28; and ABFJK = 26. With a fixed cost of $1,000/week, the initial cost is 34 weeks @ $1,000 = $34,000.
The cheapest critical-path activity is I @ $300, so reducing I from 8 weeks to 7 weeks costs $300 but saves $1,000, resulting in a net savings of $700.
The next cheapest critical-path activity is H @ $500, so reducing H from 7 weeks to 6 weeks costs $500 but saves $1,000, for a net savings of $500.
The next cheapest critical-path activity is K @ $750, so reducing K from 8 weeks to 7 weeks costs $750 but saves $1,000, for a net savings of $250.
The other two activities on the critical path are more expensive to crash than the penalty cost, so the cheapest completion time is 34 weeks - 3 weeks (I, H, K) = 31 weeks for a cost of $31,000 plus the crash costs of $300 + $500 + $750 = $32,550.

Business

You might also like to view...

How can you best prepare for potential questions that will be asked during the interview?

A) Research the organization, industry and competitors and relate your personal experience to support what the organization does. B) Research the hiring manager and relate your personal experience to support what is most important to the hiring manager. C) Prepare a list of events from your life and use them to better explain what is important to you. D) Identify areas of interest in your life and use short, direct answers to support your personal areas of interest. E) Research the organization and hiring managers and develop answers they most likely want to hear.

Business

If an asset is disposed of when it is fully depreciated and has no residual value, the business does not need to make a journal entry because the book value is zero

Indicate whether the statement is true or false

Business

According to the Society for Human Resource Management, the critical evaluation competency of HR success is defined as the ability to:

A. interpret information to make business decisions and recommendations. B. understand and apply information to contribute to the organization's strategic plan. C. direct and contribute to initiatives and processes within the organization. D. effectively exchange with stakeholders.

Business

Which of the following statements is CORRECT?

A. All else equal, senior debt generally has a lower yield to maturity than subordinated debt. B. An indenture is a bond that is less risky than a mortgage bond. C. The expected return on a corporate bond will generally exceed the bond's yield to maturity. D. If a bond's coupon rate exceeds its yield to maturity, then its expected return to investors will also exceed its yield to maturity. E. Under our bankruptcy laws, any firm that is in financial distress will be forced to declare bankruptcy and then be liquidated.

Business