Lassiter Construction charges each customer a price equal to the cost of direct materials and direct labor plus 30%. Job #17-50 included the following costs: Direct materials $50,000 Direct labor $36,000 What is price charged for Job 17-50?
A) $86,000
B) $65,000
C) $46,800
D) $111,800
E) $66,154
D
Business
You might also like to view...
Audit evidence used to support an audit opinion is obtained soley from audit procedures
a. True b. False Indicate whether the statement is true or false
Business
Business bankruptcy cases always involve fraudulent behavior
Indicate whether the statement is true or false
Business
Coalition building is getting others to support your efforts to persuade someone to do something.
Answer the following statement true (T) or false (F)
Business
In a(n) ________, executives are trained in worldwide operations, not just domestic or international operations
A) direct exporting company B) joint venture C) international division D) international subsidiary E) global organization
Business