Which of the following statements regarding time-cost tradeoffs in CPM networks is false?
A) Crashing shortens project duration by assigning more resources to critical tasks.
B) Crashing sometimes has the reverse result of lengthening the project duration.
C) Crashing must consider the impact of crashing an activity on all paths in the network.
D) Activities not on the critical path can become critical after crashing takes place.
E) A negative crash cost per period would imply that either crashing is cheaper than not crashing or that the crash time was slower than the normal time.
B
You might also like to view...
An organization focusing on the law firm segment purchases personal computers from a company, bundles together special software designed for client management and law firm accounting, and then sells the package as a turnkey system to customers
This organization is an example of: A) an original equipment manufacturer. B) a manufacturing agent. C) a value-added reseller. D) a broker.
A favorable direct materials cost variance occurs when the actual direct materials cost incurred is less than the standard direct materials cost
Indicate whether the statement is true or false
_____________ involves the use of two or more modes of transportation in moving a shipment from origin to destination
a. Intermodal transportation b. Ocean transportation c. Air transportation d. Direct service transportation
Jason worked as a manager for 30 years in a leading corporation. He now works with the Small Business Administration. As he wishes to help small business, he provides free consultation and assistance to new entrepreneurs. Jason is most likely to belong to
A. Service Corps of Retired Executives. B. Small Business Management Consultants. C. Venture capitalist companies. D. Small Business Investment Companies. E. angel investors.