Given that an activity's normal time and cost are 10 days and $400, respectively, and its crash time and cost are 5 days and $800, respectively, what is the activity's slope?

Fill in the blank(s) with the appropriate word(s).


Answer will vary

Crash cost per time unit equals the cost slope. Cost slope equals rise/run; therefore, (crash cost - normal cost)/(normal time - crash time) = ($800 - $400)/(10 - 5) = $80 per day.

Business

You might also like to view...

Which of the following are included as potential internal weaknesses in a SWOT analysis that are harmful to an organization?

A. Expanded product line, increase in demand, new markets, new regulations. B. Core competencies, market leaders, cost advantages, excellent management. C. New entrants, substitute products, shrinking markets, costly regulatory, requirements. D. Lack of strategic direction, obsolete technologies, lack of managerial talent, outdated product line.

Business

What are the four forms of organizational justice?

a. procedural, informational, interactional, and distributive b. distributive, organizational, relational, absolute c. relational, procedural, collegial, managerial d. managerial, interactional, informational, citizen

Business

To initiate a customer relationship management cycle, a company must focus on _____

a. using big data analytics to enhance the collection of customer data b. collecting detailed information about the products and services its customers are using c. identifying profitable and unprofitable customers d. transforming customer data into information that can be used to make managerial decisions

Business

In ________, an advertisement is placed in a magazine, newspaper, radio, billboard, or television and includes an order blank with a phone number, e-mail, or snail-mail address with the intent of having customers place immediate orders.

A. direct response advertising B. telemarketing C. guerilla marketing D. direct selling

Business