The late finish time (LF) is ______.

a. the latest possible date an activity can be completed without delaying the project’s completion
b. the maximum extent to which an activity can be delayed
c. the latest possible date an activity can be completed before the activity becomes irrelevant
d. the latest possible time an activity can be completed on a given day


a. the latest possible date an activity can be completed without delaying the project’s completion

Business

You might also like to view...

Telemarketing fraud usually falls into this category

a. Investment scams b. Management fraud c. Vendor fraud d. Embezzlement

Business

Which of the following is the first step in hypothesis testing based on the t statistic?

A) Select the appropriate formula for the t statistic. B) Take one or two samples and compute the mean. C) Select a significance level ? for testing. D) Refer to statistical tables. E) Formulate the null (H0 ) and the alternative (H1 ) hypotheses.

Business

In the traditional mail interview, questionnaires are mailed to random potential respondents

Indicate whether the statement is true or false

Business

Experiments on mail questionnaires for census of population revealed what about questionnaire form and layout?

A) Questions at the top of the page received more attention than those placed at the bottom. B) Sensitive information placed at the end of the questionnaire was answered more frequently than sensitive information placed elsewhere. C) Instructions printed in red made little difference except that they made the questionnaire appear more complicated to the respondents. D) Both A and C are correct.

Business