In steel erection, work cannot begin without written notification by the controlling contractor. What information must be contained in the written notification?

What will be an ideal response?


This written authorization must notify the steel erection contractor that concrete used in footings has wither: a) cured to at least 75 percent of its intended minimum compressive design strength; or b) has cured sufficiently to support the loads that will be imposed during erection.

Trades & Technology

You might also like to view...

A megohmmeter can be used to conduct resistance tests to ground.

Answer the following statement true (T) or false (F)

Trades & Technology

In a closed bid system, the number of companies invited to bid is typically limited to no more than ten contractors who are known to the owner or designers and who meet the qualification criteria set by the owner.

Answer the following statement true (T) or false (F)

Trades & Technology

Often, the completion of the landscape project at a client's present level of satisfaction sows the seed for upgrading of the same project to a higher level of satisfaction

Indicate whether the statement is true or false

Trades & Technology

The annual per capita consumption of poultry meat is around how many pounds per person today?

A. 46.8 B. 72 C. 85 D. 100.4

Trades & Technology