In which of the following situations is a state most likely to enforce a usury law?
A) X purchases two crates of liquor from a minor.
B) X sells a plot of land at a rate higher than the maximum contract rate.
C) X sends two boxes of unapproved medicines to children in Africa.
D)X charges a very high rate of interest on money borrowed by Y.
D
You might also like to view...
Solomon is currently meeting with his manager, Shayla, about his performance appraisal. He wants his nonverbal communication to convey to Shayla that he is open to her feedback. Which of the following things should he NOT do?
a. lean forward b. gesture frequently c. smile d. cross his legs
The waste that occurs from any variation in output as a result of poorly planned and designed systems is referred to as ______.
A. muri B. mura C. muda D. kaizen
Section 2-201(1) of the ________ is the basic Statute of Frauds provision for sales contracts.
A. Uniform Commercial Code (UCC) B. Sarbanes-Oxley Act C. Uniform Computer Information Transactions Act (UCITA) D. Lanham Act
A partially solved PERT problem is detailed in the table below. Times are given in weeks
Activity Preceding Optimistic Time Probable Time Pessimistic Time Expected Time Variance A -- 7 9 14 1.361 B A 2 2 8 0 C A 8 12 16 0 D A 3 5 10 1.361 E B 4 6 8 0 F B 6 8 10 0 G C, F 2 3 4 0 H D 2 2 8 1.000 I H 6 8 16 2.778 J G, I 4 6 14 2.778 K E, J 2 2 5 0.250 a. Calculate the expected time for each activity. Enter these values in the appropriate column in the table above. b. Which activities form the critical path? c. What is the estimated time of the critical path? d. What are the project variance and the project standard deviation? e. What is the probability of completion of the project after week 40?