In project management terminology, which of the following refers to the chronological representation of the time it will take to bring a project to completion?

A. storyboard
B. objectives
C. timeline
D. wireframe


Answer: C

Computer Science & Information Technology

You might also like to view...

________ is a method reference for an instance method of a class. It creates a one-parameter lambda that invokes the instance method on the lambda’s argument and returns the method’s result.

a. Math::sqrt b. System.out::println c. TreeMap::new d. String::toUpperCase

Computer Science & Information Technology

Which of the following mail clients is designed exclusively for the Macintosh platform?

a. Eudora b. Outlook c. Thunderbird d. Entourage

Computer Science & Information Technology

Which of the following is true about the Users domain local group?

a: It's in the Users folder b: It can be converted to a global group c: Domain Users is a member d: Its members can log on locally to a domain controller.

Computer Science & Information Technology

Which of the following ports should be allowed through a firewall to allow DNS resolution to occur to an outside DNS server?

A) 53 B) 20 C) 3389 D) 80

Computer Science & Information Technology