In place of a product WBS, Scrum uses product ________ as deliverables.
Fill in the blank(s) with the appropriate word(s).
features
Scrum, like other agile methods, begins with a high-level scope definition and ballpark time and cost estimates for the project. The scope and cost estimates should be complete enough that management is comfortable with the estimates. The theory is that since requirements evolve over time, detailed up-front planning will be wasted. In place of a product WBS, Scrum uses project features as deliverables.
You might also like to view...
Market _____________ are similar to market indicators, but they tend to correlate highly with market demand for a specific product.
Fill in the blank(s) with the appropriate word(s).
All report headings that are of the same level must be consistent in position, appearance, and grammatical construction
Indicate whether the statement is true or false
Critical legal studies school says that ________ are unnecessary
Fill in the blanks with correct word
On December 1, Orenthal Marketing Company received $7200 from a customer for a 2-month marketing plan to be completed January 31 of the following year. The cash receipt was recorded as unearned fees. The adjusting entry for the year ended December 31 would include:
A. a credit to Unearned Fees for $2400. B. a debit to Unearned Fees for $3600. C. a credit to Earned Fees for $4800. D. a debit to Earned Fees for $7200. E. a debit to Earned Fees for $4800.